01

APERÇU

96’’ diameter carbon steel vessel built in accordance with the requirements of the ASME Boiler and Pressure Vessel Code

SINCLAIR REFINING, a Wyoming-based oil refining company planned for a scheduled shutdown on its equipment maintenance and upgrading of capital equipment.  One such pressure vessel to be worked on is a 96’’ diameter carbon steel vessel built in accordance with the requirements of the ASME Boiler and Pressure Vessel Code with a welded 24’’ diameter dross sump at the drain bottom.  

This dross sump has become badly corroded, has been deemed unsafe for continued operation and needed to be removed and replaced with a new one.  The chosen material for the new dross sump is the high-nickel alloy Inconel.  

Our CLIENT (AZZ) is one of the main contractors upgrading the equipment on site and they need to replace a new sump with certifications and Inconel (P45) welding procedures made in accordance with the requirements of the ASME Boiler and Pressure Vessel Code.  Their main concern is the scheduled shutdown date that cannot be moved and the clock was ticking.

  • Client

    AZZ, Sinclair Refining

  • Industrie

    Petrochemical

  • Équipement

    Cuve à écume

  • Matériaux

    Acier

  • Nos Services

    Ingénierie & Fabrication

02

ENGINEERING

An Inconel weld overlay solution

The preliminary schedule presented by DIMARTECH was refused due to the long lead times for the Inconel dished head, nozzles, and flanges.  An alternate solution was needed quickly.  We proposed and offered an Inconel weld overlay solution covering internal surfaces of a carbon steel dished head and carbon steel flange faces.  An Inconel composite inserted nozzle assembly was also designed and thermal expansion growth rates for both Inconel and carbon steel were calculated and presented to the CLIENT.  

We submitted the calculations and drawings to the Authorized Inspector for ASME standards adherence and to the CLIENT for their approval.  Upon acceptance from both, we proceeded with the purchase of materials and fabrication per the newly designed sump.  Inspections included 100% full radiography, 100% PT, 100% PMI readings.

03

LIVRAISON

Project completed before critical deadline

The fabrication, inspection, testing and delivery was successfully completed on time before the deadline.  Our CLIENT received the sump at the jobsite, and welded it to the vessel on time thereby respecting their contract with the oil company.  

The collaboration between DIMARTECH and our CLIENT’s engineers resulted in the successful resolution to a situation which could have easily been detrimental to the project schedule.  Their risk factor greatly surpassed ours in this contract, and they were grateful that all technical and commercial aspects were respected. 

blue

OBTENEZ UNE ESTIMATION FERME DE VOTRE PROJET

Plan d'analyse de préfabrication

Projets connexes

Découvrez d'autres possibilités grâce au modèle de livraison d'équipement de traitement personnalisé de Dimartech, qui comprend l'ingénierie et la fabrication.
Le CLIENT avait besoin d'un fabricant de réservoirs sous pression pour concevoir et fabriquer sept (7) réservoirs sous pression de séparateurs primaires et secondaires en acier inoxydable SS304L. Les brides de jonction permettent un accès sécurisé et complet pour les opérations de mise en service et de maintenance par le personnel de l'usine.
L'adsorption par oscillation de pression est un procédé de séparation chimique dans lequel un mélange de gaz est passé à travers un lit de matériau adsorbant sous haute pression. Le CLIENT avait besoin d'un fabricant de réservoirs sous pression pour construire un ensemble de plusieurs réservoirs d'adsorbant.
Le CLIENT avait besoin d'un fabricant pour construire une unité modulaire autonome, afin d'assurer la répétabilité et l'efficacité dans leur préparation à l'entrée sur le marché. Leur modèle prototype avait évolué au fil du temps, et le défi consistait à établir des tolérances de fabrication et des dimensions pour améliorer les séquences de soudage.
FR